Project Risk Management Quiz

Project Risk Management

1 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

1. A risk response strategy that can be used for both threats and opportunities is—

2 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

2. The risk urgency is a tool and technique used for—

3 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

3. Projects are particularly susceptible to risk because—

4 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

4. As project manager, you have assembled the team to prepare a risk management plan for your project. It is to describe how risk management will be handled on your project. Within this plan, there is a—

5 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

5. You are working on identifying possible risks to your project to develop a nutritional supplement. You want to develop a comprehensive list of risks that can be addressed later through qualitative and quantitative risk analysis. A data gathering technique used to identify risks is—

6 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

6. Assume you have prepared your risk management plan, identified possible risks, analyzed them, and determined possible responses if they occur. Now it is time to Implement Risk Responses. The benefit of this process is to—

7 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

7. You are working Monitor Risks on your manufacturing project. You are fortunate to have a subject matter expert available with a specialty in risk management to assist you and your team. As you work to monitor these risks, you want to make sure your team and stakeholders are aware of—

8 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

8. Most statistical simulations of budgets, schedules, and resource allocations use which one of the following approaches?

9 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

9. A project health check identified a risk that your project would not be completed on time. You and your team are working to prevent this from occurring as you work to Implement Risk Responses. You and your team know risk management is continuous on projects, and new risks will occur. When they do occur analysis is needed, and a response strategy is determined. Your goal is to see if the strategy is executed. As you do so, you should use—

10 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

10. You are developing radio frequency (RF) technology that will improve overnight package delivery to one hour. You realize that the duration, cost, and resource requirements for a number of activities are uncertain. You want a model to represent individual project risk and other sources of uncertainty. This shows that for your next step you plan to—

11 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

11. You are determining the most effective risk response to a risk one of your team members identified. After analyzing it and including a risk management expert in the analysis process, it is evident it is a risk where the threat is such that it is outside of your authority as the project manager to determine a response. In this situation, you need to—

12 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

12. If the probability of event 1 is 80 percent and of event 2 is 70 percent and they are independent events, how likely is it that both events will occur?

13 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

13. The project scope statement should be used in the Identify Risk process because it—

14 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

14. Your project team has identified all the risks on the project and has categorized them as high, medium, and low. As you work to Monitor Risks, you want to consider all three categories as a low risk can change quickly to a medium or high risk given changes that the project may encounter. Therefore, you plan to—

15 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

15. A contingency reserve is used for—

16 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

16. The simplest form of quantitative risk analysis and modeling techniques is—

17 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

17. If a business venture has a 60-percent chance to earn $2 million and a 20-percent chance to lose $1.5 million, what is the expected monetary value of the venture?

18 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

18. You are managing the construction of a highly sophisticated data center in Southeast Asia. Although this location offers significant economic advantages, the threat of typhoons has caused you to create a backup plan to operate in Manila in case the center is flooded. This plan is an example of what type of risk response?

19 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

19. A recent earned value analysis shows that your project is 20 percent complete, the CPI is 0.67, and the SPI is 0.87. In this situation, you should—

20 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

20. The purpose of a numeric scale in risk management is to—

21 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

21. Risk score measures the—

22 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

22. In Monitor Risks the project manager, the team, and key stakeholders need to be aware of the level of risk exposure; new, changing, or outdated risks; and changes in the level of overall project risk. Information from project execution then is used to determine whether to—

23 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

23. The primary advantage of using decision tree analysis in project risk management is that it—

24 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

24. Your project is using complex, unproven technology. Your team conducted a brainstorming session to identify risks. Poor allocation of project resources was the number one risk. This risk was placed on the risk register, which included at this point a—

25 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

25. When managing current projects, it is important to use lessons learned from previous projects to improve the organization’s project management process. Therefore, in the Identify Risks process one can review the—

26 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

26. Risk mitigation involves—

27 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

27. Risk management is not a one-time process and transcends project management. Risks are first discussed as part of the—

28 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

28. Two key inputs to the Perform Quantitative Risk Analysis process are the—

29 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

29. Often in preparing the risk management plan meetings are held. The key purpose of these meetings is to—

30 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

30. As you work to Identify Risk, an item to review is—

31 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

31. A risk audit is a useful tool and technique in Monitor Risks because it—

32 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

32. Accurate and unbiased data are essential for Perform Qualitative Risk Analysis. The best approach to follow is to use—

33 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

33. Assigning more talented resources to the project to reduce time to completion or to provide better quality than originally planned are examples of which one of the following strategies?

34 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

34. You are striving to determine whether to accept a risk or transfer it to a contractor. You also may decide to just avoid the risk. You can—

35 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

35. Assume you remain unclear about what to do about a possible risk that may affect the overall project. You and your team have several strategies you can use, but before selecting one, you decide to—

36 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

36. Assume that you are working on a new product for your firm. Your CEO learned that a competitor was about to launch a new product that has similar features to those of your project. The competitor plans to launch the product on September 1. It is now March 1. Your schedule called for you to launch your product on December 1. Your CEO now has now mandated that you fast track your project, so you can launch your product on August 1. This fast track schedule is an example of an—

37 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

37. As head of the project management office, you need to focus on those items where risk responses can lead to better project outcomes. One way to help you make these decisions is to—

38 / 38

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

38. You are the project manager for the construction of an incinerator to burn refuse. Local residents and environmental groups are opposed to this project. Management agrees to move this project to a different location. This is an example of which one of the following risk responses?

Your score is

The average score is 58%

0%