1 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

1. You have been assigned as project manager on what could be a “bet the company” project. You realize that to be successful you need to exercise maximum control over project resources. You are both a manager and a leader in resource management. This means you must—

2 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

2. As the project manager, it is your goal to build a high-performing team. On your project, four of your nine team members know one another, but five are new to you and the rest of the team. As you work in team building, your objective is to—

3 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

3. Assume you are managing a large construction project to use solar power for electricity in a different country in a location that lacks easy access to transportation facilities. You must make sure all the equipment and other needed materials are available when you need them. Given the geographical location, it is a difficult task. Much of the construction equipment also is leased. As a result you need to—

4 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

4. You are leading a team to reorganize your IT department, so it is more customer oriented. Your team has 10 people. While your team members have competencies in IT, they are not in the department to promote objectivity. In your resource plan, you have a section on recognition to state when recognition and rewards will be given to members of your team. As you put this plan into practice, you should consider—

5 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

5. Which of the following factors contributes the most to team communication?

6 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

6. You are managing a virtual team. The project has been under way for several months, and you believe your team members do not view themselves as a team or a unified group. To help rectify this situation, you should—

7 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

7. Major difficulties arise when multiple projects need to be managed in the functional organizational structure because of—

8 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

8. Leadership is embedded in the job of the project manager and really in the job of every team member. Assume you are project manager with a team of two people who will work full-time on the project, and six people who will support the project on a part-time basis. All team members know one another and have worked together in the past. Leadership on this team is especially important—

9 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

9. Your organization is characterized by hierarchical organizational structures with rigid rules and policies and strict supervisory controls. Individual team members are not expected to engage in problem solving or use creative approaches to plan and execute work; management has these responsibilities. Your organization is characterized by which one of the following theories?

10 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

10. As you prepare your resource management plan, you need to provide guidance and determine the skills and capacity required to complete the activities in the project. This should be documented in the—

11 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

11. The primary purpose of effective team development is—

12 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

12. The team members on your project have been complaining that they do not have any sense of identity as a team because they are located in different areas of the building. To remedy this situation, you developed a project logo and had it printed on T-shirts to promote the project, but this action has not worked. Your next step is to—

13 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

13. You are managing a team of 120 internal members and four contractors. Given the size of this team, you want to document each team member’s assignments. You can use a—

14 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

14. Assume you are preparing your resource management plan. Your goal is to ensure each work package has an owner, who is clearly identified, and all team members understand their roles and responsibilities. The best way to show these data is by using a(n)—

15 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

15. You are managing a design and construction project for the next-generation of drones. Your organization has been the leader in the drone business since it began, which means you are fortunate as your executive realize they would only increase in capabilities and popularity and acquired needed resources in house rather than rely on contractors to preserve intellectual property. On your project, you find you are in a dilemma as you need a specific type of crane from another department. If you do not get the crane when you need it, your project’s schedule will slip dramatically. The best approach you can use in this situation is—

16 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

16. You have been a project manager for seven years. You now are managing the construction of a new facility that must comply with the government’s newly issued environmental standards. You want to ensure that your team members are able to select methods to complete various activities on the project without needing to involve you in each situation. As you prepare your resource management plan, you should document this information in which of the following—

17 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

17. It is important on all projects to determine when and how human resources will be met. Assume that you are managing a project to assess methods for streamlining the regulatory approval process for new medical devices in your government agency. Because the agency has undergone downsizing during the past three years, subject matter experts are in short supply. You must determine whether the needed subject matter experts can be acquired from inside the agency or whether you must use contractors. This information should be documented in the—

18 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

18. Conflicts are inevitable on projects, but if actually managed effectively, at times conflicts can help the team arrive at a better solution. One of the challenges a project manager faces is—

19 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

19. As project manager, you are primarily responsible for implementing the project management plan by authorizing the execution of project activities. Because you do not work in a projectized organization, you do not have direct access to human resource administrative activities. Therefore, you need to—

20 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

20. Constant bickering, absenteeism, and substandard performance have characterized the behavior of certain members of your team. You have planned an off-site retreat for the team to engage in a variety of activities. Your primary objective for investing time and money in this event is because your team—

21 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

21. Two team members on your project often disagree. You need a conflict resolution method that provides a long-term resolution. You decide to use which one of the following approaches?

22 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

22. Assume you are working to prepare your resource management plan for your automotive company. You are going to design and then manufacture state-of-the-art vehicles of various types to surpass your competitors who are focused on self-autonomous vehicles. As you prepare your plan, one area to consider is—

23 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

23. As a project manager, you believe in using a “personal touch” to further team development. One approach that has proven effective toward this goal is—

24 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

24. Your project has been under way for some time with only a few direct reports. However, it then is your responsibility to—

25 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

25. You are the project manager for a two-year project that is now beginning its second year. The mix of team members has changed, and there is confusion as to roles and responsibilities. In addition, several of the completed work packages have not received the required sign-offs, and three work packages are five weeks behind schedule. To gain control of this project, you need to—

26 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

26. You are the project manager to develop a new medical implant device. You were selected to manage this project since you are an expert in medical implant devices. However, you strive to seek opinions from others. Now you are estimating the resources you will need for this project. You consulted with an estimating expert in the company and decided the best approach is to use—

27 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

27. Having estimated the resources you need for your new medical implant project, the next challenge is to acquire them. Resources seem to always be scarce in the company. Additionally, you also work in a matrix environment, so you have limited direct control over resource selection. Your best approach is to—

28 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

28. Assume although you did your best in negotiating and influencing others to release resources to you for your medical implant project, you were not successful. You now are concerned your project, even though it had a strong business case and was approved by the portfolio group, that you now have another constraint to consider, which is—

29 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

29. Decision making often is used as a tool and technique in Acquire Project Team. One approach is multi-criteria decision tool. An example of a selection criterion to consider is—

30 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

30. Assume your team of five people to develop a data base to assess testing methods for listeria in ice cream has worked together before. You expect that this team will be a high-performing team from the beginning, but you find two team members seem to disagree as to the vison of the project. You meet with these two people and find one of them really dislikes being on the project. You decide to ask your sponsor if this person can be reassigned, and another person added to the team. The sponsor agrees. This means—

31 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

31. Your organization is adopting a project-based approach to business, which has been difficult. Although project teams have been created, they are little more than a collection of functional and technical experts who focus on their specialties. You are managing the company’s most important project. As you begin this project, you must place a high priority on—

32 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

32. Your company just learned it won a competitive proposal from your government to design a better safety system for food products in your country since there are not enough resources to inspect the imported food. You were listed in your company’s proposal as the project manager since you have your PMP. You now are establishing your project team. You should consider—

33 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

33. Now that your project to develop the next generation prostate cancer drug is under way, you have gotten to know your team members and the skills and competencies they have. You now are in a position to assess their strengths and any areas of improvement. You decided one approach to use with more junior level team members was—

34 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

34. Work performance reports are especially helpful in the Manage Team process because—

35 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

35. Although most organizations conduct individual work performance reviews and appraisals, most of our work is done through teams. You decided since you have the luxury of a team of six people who are full-time to conduct an individual assessment but to concentrate on a team performance assessment. An example of an indicator you plan to use is—

36 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

36. You are working to estimate the activity resources you need for your new passenger train that your company will develop, own, and operate. It is to be able to travel at the speed of light, be quiet, and to be luxurious with no breakdowns in service. The goal is to test its appeal along a busy interstate highway system with stops only in three major cities. As you do so, you determined it would be helpful in addition to determining the needed resources to prepare a(n)—

37 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

37. A key benefit of the Plan Resource Management process is to determine the project organization chart. Therefore, an important first step is to—

38 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

38. Assume you decide to prepare a role-responsibility-authority form as you work on your project resource management plan. This form—

39 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

39. Assume you are estimating the activity resources you will need to make dirigibles a safe and fast way to travel. For this project, you will need a number of specialists as well as generalists to communicate externally as to the value of using a dirigible and its safety record. You also will need materials and equipment. As you work to estimate the resources, you believe it would be useful to consider—

40 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

40. Determining the method and the timing of releasing team members should be included in the—