Project Cost Management Quiz

Project Cost Management Quiz

1 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below, to answer questions 1 through 4:
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000

1. According to earned value analysis, the SV and status of the project described above is—

2 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below, to answer questions 1 through 4:
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000

2. What is the CPI for this project, and what does it tell us about cost performance thus far?

3 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below, to answer questions 1 through 4:
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000

3. The CV for this project is—

4 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below, to answer questions 1 through 4:
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000

4. What is the EAC for this project, and what does it represent?

5 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

5. You have now prepared your cost management plan so now you are preparing your project’s cost estimate. You decided to use analogous estimating. Analogous estimating—

6 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

6. While cost estimates are the main output of the Estimate Costs process, not to be overlooked is—

7 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

7. You must consider direct costs, indirect costs, overhead costs, and general and administrative costs during cost estimating. An example of an indirect cost is—

8 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

8. If the cost variance is the same as the schedule variance and both numbers are greater than zero, then—

9 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

9. You are responsible for preparing a cost estimate for a large World Bank project. You decide to prepare a bottom-up estimate because your estimate needs to be as accurate as possible. Your first step is to—

10 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

10. Management has grown weary of the many surprises, mostly negative, that occur on your projects. In an effort to provide stakeholders with an effective performance metric, you will use the to-complete performance index (TCPI). Its purpose is to—

11 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

11. If operations on a work package were estimated to cost $1,500 and finish today but, instead, have cost $1,350 and are only two-thirds complete, the cost variance is—

12 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

12. When you review cost performance data on your project, different responses will be required depending on the degree of variance or control thresholds from the baseline. For example, a variance of 10 percent might not require immediate action, whereas a variance of 100 percent will require investigation. A description of how you plan to manage cost variances should be included in the—

13 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

13. As of the fourth month on the Acme project, cumulative planned expenditures were $100,000. Actual expenditures totaled $120,000. How is the Acme project doing?

14 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

14. On your project, you need to assign costs to the time period in which they are incurred. To do this, you should—

15 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

15. You have a number of costs to track and manage because your project is technically very complex. They include direct costs and indirect (overhead) costs. You have found that managing overhead costs is particularly difficult because they—

16 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

16. If you want to calculate the ETC based on the assumption that work is proceeding as planned, the remaining work can be calculated by which of the following formulas?

17 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

17. You receive a frantic phone call from your vice president who says she is going to meet with a prospective client in 15 minutes to discuss a large and complex project. She asks you how much the project will cost. You quickly think of some similar past projects, factor in a few unknowns, and give her a number. You provided which of the following type of estimate—

18 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

18. Your approved cost baseline has changed because of a major scope change on your project. Your next step should be to—

19 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

19. You have set aside a certain portion of your project for contingency and management reserves. You want to use these reserves to cover the costs of risk responses or other contingencies. On your project, you have had some opportunities that resulted, which means you should—

20 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

20. There are many useful EVM metrics, but the most critical is—

21 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

21. The approved, integrated scope-schedule-cost plan for project work is—

22 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

22. It is expensive to lease office space in cities around the world. Office space can cost approximately USD $150 per square foot in Tampa, Florida. And it can cost approximately ¥50,000 per square meter in Tokyo. These “averages” can help a person to determine how much it will cost to lease office space in these cities based on the amount of space leased. These estimates are examples of—

23 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

23. Your project manager has requested that you provide him with a forecast of project costs for the next 12 months. He needs this information to determine if the budget should be increased or decreased on this major construction project. In addition to the usual information sources, which of the following should you also consider?

24 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

24. There are a number of different earned value management rules of performance measurement that can be established as part of the cost management plan. One of them is the—

25 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

25. Which of the following calculations CANNOT be used to determine EAC?

26 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

26. Typically, the statement “no one likes to estimate, because they know their estimate will be proven incorrect” is true. However, you have been given the challenge of estimating the costs for your nuclear reactor project. You are considering a variety of items as you incorporate the cost of financing, which is in the—

27 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

27. By reviewing cumulative cost curves, the project manager can monitor—

28 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

28. Control accounts—

29 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

29. Assume you are holding performance review meetings on your project to assess schedule activity and work packages over-running or under-running the budget and to determine any estimated funds needed to complete work in progress. You also are using earned value. You are preparing reports for your stakeholders as they want regular cost forecasts. This means they are interested in—

30 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

30. Overall cost estimates must be allocated to individual activities to establish the cost performance baseline. In an ideal situation, a project manager would prefer to prepare estimates—

31 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

31. One way to engage team members to improve estimate accuracy is to—

32 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

32. Assume you have used reserve analysis as a tool and technique in Control Costs. However, during your project risk identification and subsequent analysis of the identified risks was ongoing. In fact you had a risk expert on your team. This means you may need to—

33 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

33. Increased attention to return on investment (ROI) now requires you to re-estimate the costs for your project. When you looked at how costs were first estimated, you realized an order-of-magnitude estimate was prepared, which was never refined. Therefore, now you are estimating costs from the beginning. As you are preparing a new smart TV along with an automated home as the products of your project, you realize market conditions should be reviewed because—

34 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

34. A revised cost baseline may be required in cost control when—

35 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

35. As project manager, you identified a number of acceptable tolerances as part of your earned value management system. During execution, some “unacceptable” variances occurred. After each “unacceptable” variance occurred, a best practice is to—

36 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

36. Assume that the project cost estimates have been prepared for each activity and the basis of these estimates has been determined. Now, as the project manager for your nutrition awareness program in your hospital, you are preparing your budget. Because you have estimates for more than 1,200 separate activities, you have decided to first—

37 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

37. Assume you are using earned value on your project, and as of today, your cumulative CPI is below the baseline. This means—

38 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

38. Assume it has become obvious on your project that the budget at completion is no longer viable. This means as the project manager, you should—

39 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

39. Assume that your actual costs are $800; your planned value is $1,200; and your earned value is $1,000. Based on these data, what can be determined regarding your schedule variance?

40 / 40

INSTRUCTIONS: Note the most suitable answer for each multiple-choice question.

40. The CPI on your project is 0.84. This means that you should—

Your score is

The average score is 50%

0%